Deterministic scheduling of wafer fab operations
Abstract
In this paper, we present a modification of the Shifting Bottleneck heuristic (MSB) for scheduling wafer fabrication facilities. Implementing a determinstic scheduling approach within a simulation model (ASAP) is nontrivial. The simulation model serves as the MES system emulator in addition to performing traditional simulation tasks. Implementation issues as well as results of the MSB are presented.